Centre for Clean Energy and Automotive Innovation
Construction
VCC’s North parking lot between Great Northern Way and 7th Avenue, the location of the new building, has been closed since June for site preparations.
As construction commences, we ask for your patience and understanding as we work towards enhancing our facilities for future generations of students.
Timeline
Construction for the CCEAI has been underway since June 2024. Here are some key dates (dates are approximate and are subject to change):
Tree removal | July-August 2024 |
---|---|
Site clearing and demolition | July-August 2024 |
Pipe piling | July-August 2024 |
Excavation and shoring | July 2024-June 2025 |
PLEASE NOTE: During these phases, particularly piling and excavation, expect significant noise disruptions and increased large truck activity entering and exiting the construction site.
Parking impacts
Paid parking spaces are available in VCC's parking lot east of Building B (located along Keith Drive). Please obtain a VCC parking permit from the security desk on Level 2 of Building B. A student or employee ID will be verified by security staff before a permit is issued.
There are approximately 90 stalls, including 4 EV stalls for short-term charging. Drop off parking will remain available and designated for McGregor Daycare use only.
Street parking is available in the surrounding neighbourhood. Please ensure you adhere to the City of Vancouver’s parking by-laws. Consider walking, cycling, using a ride-share, or taking transit to get to the Broadway campus.
Project partners
The CCEAI is designed by Stantec and RJC Engineers in collaboration with Two Row Architect (Indigenous design collaborator).
Bird Construction is the general contractor for the project.
Questions or comments? Please contact us.